Construction of main gas pipeline, section 1 "Klechovce-Block station 5 (Stip)"

PROJECT DETAILS


The construction of the main gas pipeline Section 1 "Klechovce - Block Station 5" is a realization of the Agreement between the Government of the Republic of Macedonia and the Government of the Russian Federation on regulating the obligations of the former USSR after the calculations related to trade between the former USSR and the former SFRY.06. 2010 in St. Petersburg. The constructed gas pipeline in the length of 61 km, diameter of the pipe DN 500 (20 ”),
Project timeline:
Start 09.07.2014
Anticipated end 19.06.2016
End
Start date:
09.07.2014
End date:
Completion date:
19.06.2016
Type of project:
Institution:
Non-Budget Users
Municipality:
Shtip
Budget program:
АКЦИОНЕРСКИ ДРУШТВА


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Обезбедување погодна деловна клима во планските региони1.201.047.273,001.201.047.273,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Други извориНационални енергетски ресурси3.603.141.817,00Спогодбата меѓу Владата на Република Македонија и Владата на Руската Федерација за регулирање на обврските од поранешниот СССР