COORDINATION SYSTEM IN PLANNING, IMPLEMENTATION, MONITORING AND EVALUATION OF POLICY FOR BALANCED REGIONAL DEVELOPMENT

Reconstruction of road infrastructure in the municipalities of Dolneni and Krivogashtani

PROJECT DETAILS


The existing condition of both roads is unsuitable, so it can be said that they are in good condition to accomplish their purpose, the users of these roads face daily problems in terms of their passability. Road from p. Pashino Ruvci on Regional Road R 2339 has a length of 1315.26 m and is a connection between (Llagovo - Vogjan i-Buçin - Demir Hisar). The road has a land road with large deformations so that the movement of citizens and the flow of traffic is very difficult. This road is of great importance for the inhabitants of the municipality of Krivogashtani and the wider region because it is a connection of the inhabitants of the village. Pashino Ruvci and the surrounding settlements from Krivogashtani with the discovery route from Prilep to Demir Hisar. Reconstruction of this road will shorten the road for residents traveling through the local road Çepigovë - Pashino Ruvci to Prilep by about 2.5 km. The connection of the inhabitants of the gravitational settlements in the municipality of Krivogashtani and the neighboring municipalities of Prilep and Demir Hisar will be improved and the flow of goods and services provided in the regional livestock and green market in Krivogashtani will be enabled. Also, residents who come through the regional road R2339 from the settlements Kadino Selo, Galicani, Llagovo and others from the municipality of Prilep and go to Çepigovo, Trojkrsti, Topolcani on the highway Prilep - Bitola can use this shortened road and avoid the frequency of existing regional road. The project includes phase 3 in length of 383 m, which complements the previous phases already completed. This road is of great importance for the inhabitants of the municipalities of Krivogashtani, Prilep, Krushevo and Demir Hisar. In the municipality of Dolneni there is a street in p. Llazhan in length 1103 m which in a small part is asphalted 40 years ago, while the rest is macadam, the part that is asphalted is 75% damaged and the macadam is completely destroyed, which is a serious problem for normal traffic. There is no suitable outlet, so when it rains and snows, there is flooding, which consequently creates large amounts of mud which further reduces permeability. This road is used every day by the inhabitants of Lazani, Zhitoshë, Borinë, Jakrenovë, Sazdevë and Debreshtë. In addition, this road connects the primary school Mirce Acev and the religious building St. Nicholas where there is a cemetery with the regional road R 2335, and through it with other settlements in the municipality of Dolneni and neighboring municipalities of Krivogashtani, Prilep and Makedonski Brod. All of the above give a significant social and economic aspect to this road.
Project timeline:
Start 14.02.2020
End 26.11.2020
Anticipated end 30.11.2020
Start date:
14.02.2020
End date:
30.11.2020
Completion date:
26.11.2020
Type of project:
Патен сообраќај
Institution:
Bureau for Regional Development
Municipality:
Dolneni
Budget program:
РЕГИОНАЛЕН РАЗВОЈ


Strategic measures

Strategic measureAllocated amount by projectsCompleted amount by projects
Подигнување на капацитетот на планските региони за препознавање, промовирање и реализирање на потенцијалот за инвестиции во планските региони8.502.639,006.294.378,00


Indicators



Finance

Financing sourceInstitutionAmountNote
Буџет на државатаБИРО ЗА РЕГИОНАЛЕН РАЗВОЈ8.502.639,00 
Буџет на единицата на локалната самоуправа 836.160,00 
Република Северна Македонија Влада на Република Северна Македонија